Last updated 11 August 2026 · 15 of 96 items complete across all properties · ← Back to Team Hub
| Task | Status |
|---|---|
| Replace broken roof tiles |
|
| Re-bed & re-point damaged ridge capping |
|
| Rectify damaged mortar |
|
| Secure loose tiles throughout |
|
| Remove and replace defective silicone |
|
| Repair and secure lifted flashing to restore weatherproofing |
|
| Task | Status |
|---|---|
| Demolish existing garage (after asbestos is removed) |
|
| Task | Status |
|---|---|
| Pick up and install gate |
|
| Ensure full coverage in area behind striker plate in hinged doors |
|
| Build landing approx 400mm above ground level under clothesline. Do not modify existing garden |
|
| Replace rear garden tap with external grade screws |
|
| Replace front door hinges with black ones (now on site) |
|
| Patch damage to wall in back bedroom next to wardrobe |
|
| Plumber: fix RWT/stormwater in general |
|
| Wardrobe contractor: replace bent bottom rail to wardrobe door |
|
| Task | Status |
|---|---|
| Install gutter guard |
|
| Add 2 x subfloor vent fans directly across from one another. i.e. rear patio and front facade |
|
| Install black plastic to any accessible part of the subfloor, pinned to the dirt |
|
| Task | Status |
|---|---|
| Build retaining wall along the boundary as per plan |
|
| Create barricade around driveway over drain |
|
| Task | Status |
|---|---|
| Paint over rusted sections of roof. Approx 6 small sections |
|
| Lay new turf on ungrassed areas |
|
| Level disturbed soil under house |
|
| Paint new pink trim near sliding door area |
|
| Bog and paint pink mouldings to edge of eave |
|
| Paint downpipe |
|
| RAMTIN. Finish front garden planting, geofabric + white pebbles on top |
|
| Paint patio edge |
|
| Buy and install IN1142222 flashing to sides of front pergola roof to act as a barge capping |
|
| Replace rusted gutter brackets |
|
| Electrician: Install wall light to front façade where old one used to be (see attached photo) (replace other 2 to match) |
|
| Task | Status |
|---|---|
| Bricklayers to conduct site clean. |
|
| Bricklayers to swap out bricks over garage which are incorrectly laid. |
|
| Put washers to bolts holding down steel posts |
|
| Put Ankascrews next to any dynabolts where a washer didn’t fit |
|
| Drop the ceiling in the front patio areas |
|
| Existing pergola – Replace any timber within 900mm of new property boundary with steel. Replace flashing with correct corrugated flashing cut out. Ensure roof sheets do not lap more than one corrugation |
|
| Blocking to joists where span exceeds 3.6m |
|
| Gutter and downpipe to existing house’s awning |
|
| Extensive Site clean |
|
| Take Acroprops back to Jilliby or Boolaroo |
|
| Finish joist hanger install |
|
| Task | Status |
|---|---|
| Repaint houses and roofs |
|
| Run ag drain to kerb with kerb adapter |
|
| Remove dead branches, remove excessive plants from the garden for achieve a minimalist look |
|
| Paint both houses and eaves etc. |
|
| Pressure wash fence panels, remove vegetation, replace fence panels that don’t match in colour |
|
| Separate plumbing and electric (if subdivision happening) |
|
| Replace bedroom flooring in house |
|
| Replace flooring throughout granny flat |
|
| Tile granny flat patio |
|
| Tile courtyard outside kitchen/old laundry (house) |
|
| Ensure stormwater from house does not crossover into granny flat’s land (subdivision is proposed) |
|
| Repaint houses and roofs |
|
| Spread insulation in roof space (bags of it are already in there) |
|
| Lay tiles to top of brick retaining wall to achieve a nice finish |
|
| Task | Status |
|---|---|
| Seal around plumbing penetration from hot water system in rear laundry area |
|
| Spray tops of cut color bond posts with classic cream paint |
|
| Install rubber door stop to rendered wall outside kitchen screen door |
|
| Splay last colorbond fence piece so the step down is eliminated |
|
| Install larger steel brackets and BOLTS (not screws) to each fence post between house and granny flat, both sides of the post, to solidify fence |
|
| Put screws in fence posts wherever they’re missing |
|
| Task | Status |
|---|---|
| Waterfall edge to laundry joinery |
|
| Install kickboard to laundry joinery |
|
| Cut 2 x holes in laundry cupboard (see attached) |
|
| Run power through one hole + washing machine waste through the other |
|
| Cut hole right below GPO in laundry wall cupboard (see photo) |
|
| Plumber: Connect waste pipe to sewer pipe |
|
| Install curtains to front door |
|
| Duct rangehood through cupboards and out of new 450mm cupboard |
|
| Install 450mm wall cupboard between kitchen window and existing cupboard |
|
| Install strap bracing to support hanging rails |
|
| Cut out side of sink cupboard to provide access to corner cupboard |
|
| Silicone benchtop to wall |
|
| Finish kitchen joinery install |
|
| Silicone kitchen benchtop join with grey sealant |
|
| Add 2 x footings as per attached photo |
|
| Task | Status |
|---|---|
| Install lock to bathroom barn door |
|
| Task | Status |
|---|---|
| Build deck at rear of granny flat (Use 240mm from relocatable home) |
|
| Put new male to male attachments to shorten the sprinklers on septic system |
|
| Use strap bracing to brace the legs of the building to stop movement |
|
| Pressure wash outside cladding facing south |
|
| Task | Status |
|---|---|
| Install letterbox onto opposite side of driveway |
|
| Install recessed door handles to ensuite barn door |
|
| General site clean (FC sheet, plywood, metal sheets etc.) |
|
| Replace damaged boundary fence timber near chicken coop |
|
| Ramtin: Paint (not stain) all hardwood |
|
| Replace bin area timbers and the entire garden bed altogether |
|
| Fix/replace balustrade wire to rear bedroom deck |
|
| Reinstall gutter guard |
|
| Task | Status |
|---|---|
| Apply sealant to inside of gutter to stop leak |
|
| Fill low patches in front yard with top soil (10-20mm layers every 4 weeks) |
|
| Cut capping to suit front retaining wall, glue it back together so it has a return on both sides, then glue it to the top of the retaining wall |
|
| Apply sealant to inside of gutter to stop leak |
|
| Put timber on one side of manhole (timber already on site) |
|
| Cut down steel H posts to be 5mm lower than sleepers |
|
| Spray cut tops with gal spray |
|
| Level backyard |
|
| Task | Status |
|---|---|
| Re-install insulation in ceiling prior to Gyprocking |
|
| Bring saw horse + planks back to Jilliby when we hire the truck |
|
| Dig around outside of elevator shaft to enable waterproofer to waterproof slab edge |
|
| Hire truck and bring leftover materials to Jilliby (plywood, bricks, joists etc.) |
|
| Non shrink structural grout to brick overhangs |
|
Change a task's status using the dropdown — it updates ClickUp directly. Click a property to expand its list. Not linked from the site menu or search results — accessible only via direct URL.