Construction Schedule

Construction Schedule

Last updated 11 August 2026 · 110 of 262 items complete across all jobs · ← Back to Team Hub

To DoIn ProgressAt Risk / Needs AttentionComplete
62 Macquarie St, Wallsend31 of 144 complete

Site Establishment & Slab

Date Task Status
TBC Mine Subsidence Inspection for pre-slab pour (book 48hrs in advance)
12 Jul 2026 Construction Deposit Paid
13 Jul 2026 Council Contributions Paid
14 Jul 2026 Release Frame
14 Jul 2026 Construction start scheduled and client advised of start date and neighbour notification letter box drop.
18 Jul 2026 Release Windows
19 Jul 2026 Release appliances
19 Jul 2026 Release PC items and vanities order
19 Jul 2026 Release mixers
19 Jul 2026 Release electrical and AC package
19 Jul 2026 Release plumbing package
19 Jul 2026 Release kitchen
19 Jul 2026 Release pest collars and perimeter protection
19 Jul 2026 Release electrical conduits
19 Jul 2026 Release internal drainage
19 Jul 2026 Release concrete package
19 Jul 2026 Release screw piers
19 Jul 2026 Release Site cut excavation
19 Jul 2026 Release Site Set Out
21 Jul 2026 Survey set out
24 Jul 2026 Site cut excavation
29 Jul 2026 Foundation Inspection by Mine Subsidence Board & Engineer to suffice conditions 6 & 7
29 Jul 2026 Bored piers
31 Jul 2026 Formwork
2 Aug 2026 Mine Subsidence Board & Engineering Inspection of Footings
4 Aug 2026 Electrical conduits
4 Aug 2026 Internal drainage
5 Aug 2026 Pest collars
7 Aug 2026 Progress Claim – Slab
7 Aug 2026 Pour concrete

Frame

Date Task Status
8 Aug 2026 Release stairs
8 Aug 2026 Release lock up material
8 Aug 2026 Release brickie fatty sand
8 Aug 2026 Release brick hardware
8 Aug 2026 Release bricks
8 Aug 2026 Release bricklaying PO
8 Aug 2026 Certifier inspection & Mine Subsidence Inspection
8 Aug 2026 Pods and steel
12 Aug 2026 Slab Curing
18 Aug 2026 Pest perimeter protection
19 Aug 2026 Ground floor frame and floor system delivery
22 Aug 2026 Stand ground floor frames
24 Aug 2026 Lock up material delivery
25 Aug 2026 Release scaffold
25 Aug 2026 First floor frames & truss delivery
26 Aug 2026 Install entry jambs, doors & cavity slider units
26 Aug 2026 Progress Claim – Frame
26 Aug 2026 Crane lift for first floor frame & trusses
26 Aug 2026 Windows Delivery

Lock Up

Date Task Status
28 Aug 2026 Stand first floor frame & trusses
29 Aug 2026 Release garage door
29 Aug 2026 Release roof
29 Aug 2026 Switch board install
31 Aug 2026 Stairs measure
31 Aug 2026 Garage door measure
31 Aug 2026 Brickie sand delivery
31 Aug 2026 Brick hardware delivery
31 Aug 2026 Brick delivery
7 Sep 2026 Brickwork ground floor
10 Sep 2026 Release watertank
10 Sep 2026 Release heat pump
10 Sep 2026 Release eaves & cladding carpenter PO
10 Sep 2026 Release eaves & cladding material
10 Sep 2026 Scaffold erection
11 Sep 2026 Roof measure
12 Sep 2026 Kitchen measure
13 Sep 2026 Measure up flashings & order
13 Sep 2026 Fascia & gutter installation
14 Sep 2026 Release plasterboard
14 Sep 2026 Release insulation
14 Sep 2026 Release external & internal painting PO
14 Sep 2026 Roof installation
17 Sep 2026 Eaves & cladding delivery
18 Sep 2026 Progress Claim – Lock Up
18 Sep 2026 Eave and cladding installation

Fix Out

Date Task Status
19 Sep 2026 Install z flashings
20 Sep 2026 Downpipes install FF
24 Sep 2026 External painting eaves & cladding
25 Sep 2026 Scaffold dismantlement
25 Sep 2026 Release tiles
25 Sep 2026 Release fix out carpenter PO
25 Sep 2026 Release fix out material
25 Sep 2026 Mixers delivery
26 Sep 2026 Plumbing rough in
27 Sep 2026 Electrical rough in
28 Sep 2026 Release stone benchtops
28 Sep 2026 Release showerscreens and wardrobes
28 Sep 2026 Release waterproofing PO
28 Sep 2026 Certifier frame inspection
28 Sep 2026 Plumbing mains install
28 Sep 2026 Electrical mains install
1 Oct 2026 Release carpet supply & install PO
1 Oct 2026 Release floating floors material
1 Oct 2026 Release floating floors install PO
1 Oct 2026 Release driveway PO
1 Oct 2026 Rectify framing defects as per certifier inspection
2 Oct 2026 Insulation install
5 Oct 2026 Plasterboard install
8 Oct 2026 Fix out delivery
8 Oct 2026 Electrical cut out
9 Oct 2026 Progress Claim – Fix Out
9 Oct 2026 Fix out install

Fit Off

Date Task Status
10 Oct 2026 Garage door install
11 Oct 2026 Release window service and flyscreens
12 Oct 2026 Tile delivery
14 Oct 2026 Internal painting
16 Oct 2026 Waterproofing install
17 Oct 2026 Certifier waterproofing inspection
21 Oct 2026 Tiling install
22 Oct 2026 Appliances delivery
22 Oct 2026 Showerscreens and wardrobes check measure
23 Oct 2026 Kitchen & joinery installation
24 Oct 2026 Driveway inspection by Council
24 Oct 2026 Watertank delivery
24 Oct 2026 Heat pump delivery
24 Oct 2026 PC items and vanities delivery
24 Oct 2026 Stone benchtops check measure
25 Oct 2026 Plumbing fit off
26 Oct 2026 Progress Claim – Fit Off
26 Oct 2026 Driveway install
26 Oct 2026 AC fit off
26 Oct 2026 Electrical fit off

Practical Completion

Date Task Status
29 Oct 2026 Install showerscreens
29 Oct 2026 Install robes
31 Oct 2026 Stone benchtops install
1 Nov 2026 Measure up and order blinds
1 Nov 2026 Install tile splashbacks
2 Nov 2026 Window service and flyscreens install
5 Nov 2026 Release final clean
7 Nov 2026 Install floating floors
7 Nov 2026 Landscaping
8 Nov 2026 Blinds delivery
9 Nov 2026 Install blinds
9 Nov 2026 Install carpets
12 Nov 2026 Final clean
13 Nov 2026 A to Z Homes defects walkthrough
14 Nov 2026 Paint touch ups
14 Nov 2026 Rectify defects
15 Nov 2026 Progress Claim – Practical Completion
15 Nov 2026 Certifier PC Inspection

Handover

Date Task Status
16 Nov 2026 Client defects walkthrough
19 Nov 2026 Receive final payment from client
19 Nov 2026 Rectify defects
20 Nov 2026 Handover meeting with client
197 Cessnock Road, Abermain79 of 118 complete

Site Establishment & Slab

Date Task Status
3 Mar 2025 Site setup
4 Mar 2025 Set out survey
28 Mar 2025 Get new slab and frame engineering
16 Sep 2025 Excavation
4 Nov 2025 Excavate piers
15 Sep 2025 Certifier inspection
20 Sep 2025 Pour piers
22 Sep 2025 Internal drainage
7 Oct 2025 Pest collars
3 Nov 2025 Apply termite poison to soil under building footprint
21 Oct 2025 Steel and pod delivery
31 Oct 2025 Formwork and steel erection
31 Oct 2025 Electrical conduit in slab for mains and gondolas
3 Nov 2025 Turn up reo bar in slab to earth
4 Nov 2025 Formwork check by surveyor
4 Nov 2025 Inspection by certifier and engineer
6 Nov 2025 Concrete pour
7 Nov 2025 Water the slab on client’s request (use timed sprinklers)
18 Nov 2025 Pest perimeter

Frame

Date Task Status
19 Nov 2025 Order fasteners (TF bolts and TF washers) for steel frame
18 Nov 2025 Ground floor frame and floor system delivery (tell carpenters to be there)
26 Nov 2025 Window delivery
26 Nov 2025 Check circulation space in front of toilet
26 Nov 2025 Order electricity account connection
1 Dec 2025 Steel frame delivery
4 Feb 2026 Order NBN connection
5 Jan 2026 Christmas break
12 Jan 2026 Install meterboard
3 Feb 2026 Ground floor frame and floor system erection
30 Jan 2026 First floor frame and truss delivery
10 Feb 2026 Crane lift for first floor frames and trusses
10 Feb 2026 Install FCID if it remains externally mounted
13 Feb 2026 Erect first floor frame and trusses

Lock Up

Date Task Status
11 Feb 2026 Lock up delivery then sarking to outside of building
12 Feb 2026 Staircase measure, quote and install
16 Feb 2026 Kitchen check measure
16 Feb 2026 Block out for disabled bathroom rails
17 Feb 2026 Scaffold quote
16 Feb 2026 Modify frame to suit commercial door from existing pharmacy?
16 Feb 2026 Install awning flashing before brickwork? how will brickwork be supported along the front?
16 Feb 2026 Brace upstairs walls with timber beam/offcuts between storage rooms and external walls
16 Feb 2026 Roof check-measure
16 Feb 2026 Brick delivery
16 Feb 2026 Brick auxiliary item delivery
16 Feb 2026 Sand delivery
2 Mar 2026 Bricklaying – ground floor
26 Feb 2026 Commercial front door check-measure?
11 Mar 2026 Telstra power pole reconnection
16 Feb 2026 Install 2 x hinged external doors
11 Mar 2026 Scaffold erection
17 Apr 2026 Bricklaying – first floor
17 Apr 2026 Staircase install

Fix Out

Date Task Status
15 May 2026 Any plumbing and electrical rough ins required prior to ground floor ceiling install (i.e. sewer stack from first floor)
20 Apr 2026 Install fire rated ceiling to ground floor (after stair install)
20 Apr 2026 Install Z flashing transition from brickwork to cladding
20 Apr 2026 Scaffolding modification
7 Apr 2026 Roof install
5 May 2026 Get wall mixers to site
22 May 2026 Downpipe, stink pipe and any other plumbing elements to be installed
15 May 2026 TV antenna and any other electrical elements to be installed
3 Jun 2026 Ensure second floor waste to cleaning room upstairs
15 May 2026 Solar panel rough in (by client, if he wants to have solar)
15 May 2026 AC rough in (provisions only. AC no longer part of A to Z Homes scope)
15 May 2026 Plumbing rough in. Note fire rated ceilings. Check disabled bathroom measurements
18 May 2026 Eave install/lock up install/block out as required
29 May 2026 Electrical rough in including fire provisions and data points. Note fire rated ceilings
19 May 2026 Mains quote. 2 electrical meters required
13 May 2026 Brick cleaning
3 Jun 2026 Site meeting with owner to approve electrical rough in
21 May 2026 Eave, downpipe and other elements to be painted
22 May 2026 Frame inspection by certifier
3 Jun 2026 Rectify any framing issues
14 May 2026 Caulk brick joints
14 May 2026 Brick touch-ups after clean
2 Jun 2026 Electrical mains
2 Jun 2026 Plumbing mains
24 Jun 2026 Scaffold dismantling
16 Jun 2026 Insulation install. Offer Ehab floor insulation for acoustic purposes?
26 Aug 2026 Plasterboard install including fire rated ceiling
27 Aug 2026 Electrical cut out
21 Jul 2026 Mould out delivery
31 Aug 2026 Mould out
1 Sep 2026 Commercial door install

Fit Off

Date Task Status
10 Sep 2026 Painting
11 Sep 2026 Remove Fall Stop
14 Sep 2026 Install Staircase Handrail
14 Sep 2026 Blind order
31 Aug 2026 Tile delivery
14 Sep 2026 Waterproofing (including slab edge to elevator shaft)
14 Sep 2026 Waterproofing inspection by certifier
15 Sep 2026 Order vanity from Beaumont Tiles
15 Sep 2026 Begin compiling OC certificates
2 Oct 2026 Tiling
5 Oct 2026 Showerscreen check measure
7 Oct 2026 Kitchen and joinery install
8 Oct 2026 Kitchen bulkhead install
8 Oct 2026 Stone benchtop check measure
8 Oct 2026 Supply cooktop and sink to stone mason
19 Oct 2026 Benchtop install
12 Oct 2026 Shower-screen install
20 Oct 2026 PC item delivery (get IN0122160 flood lights from Bunnings if we should go the extra mile)
19 Oct 2026 Heat pump delivery
19 Oct 2026 Vanity delivery (1 x Goulburn vanity from Beaumont Tiles)
7 Oct 2026 Electrical fit off
23 Oct 2026 Plumbing fit off
21 Oct 2026 Tile splashback
14 Oct 2026 Window Service
3 Sep 2026 Driveway
2 Sep 2026 Fencing
23 Oct 2026 Blind install

Practical Completion

Date Task Status
27 Oct 2026 Defects/detailing by carpenter
26 Oct 2026 Paint touch ups
28 Oct 2026 Final inspection by certifier
28 Oct 2026 Final clean
29 Oct 2026 Defect walk-through with client
5 Nov 2026 Rectify defects

Handover

Date Task Status
6 Nov 2026 Receive final payment from client
13 Nov 2026 Handover meeting with client

Schedule sourced from Smartsheet. Change a task's status using the dropdown \u2013 it saves here (not synced back to Smartsheet or ClickUp).

Change a task's status using the dropdown — it updates ClickUp directly. Click a job to expand its schedule. Not linked from the site menu or search results — accessible only via direct URL.